THE ASK
Toys “R” Us engaged Ace3 to shepherd multiple projects to upgrade commerce infrastructure and streamline operations in the UK and Poland.
THE OUTCOME
Ace3 took over the data center migration project from a major vendor.
We provided geographical failover strategy without adding operational costs.
Focused on Oracle Commerce stack (Endeca, BCC, CSC, and Commerce) as well as various third party integrations.
Performed load testing cycles to stabilize and boost site performance for the holidays.
Implemented responsive UI design for TRU UK site.
BUSINESS OUTCOMES
Achieved cost savings for UK and POL commerce upgrade projects
Trimmed the timeline for implementation from eight to three months
Responsive UI design
Site stabilization
Performance tuning
Established confidence among TRU executives and expanded engagement across international markets